Fenómeno del problema
When small PPO products are produced on large machines, degradation problems occur frequently, and when large products are produced on small machines, filling is insufficient; equipment and product matching is improper.
Análisis de la causa
PPO is sensitive to residence time; small products on large machines cause the melt to reside at high temperature for a long time and degrade; large products on small machines have insufficient shot size and plasticizing capacity; the matching principle is that product weight accounts for a reasonable proportion of the machine.
Solución
①Match machine shot size according to product weight; ②avoid excessively large machines for small products; ③calculate plasticizing capacity to meet cycle requirements; ④consider material characteristic constraints in production scheduling.
Conclusión clave
Machine matching in PPO production scheduling directly affects degradation risk; residence time management starts from equipment selection; production planning needs process participation.; After confirming effectiveness, fix the parameters and practices into the work instruction to prevent recurrence
PPO; machine matching; shot size; residence time; degradation; production scheduling