POM First Article and Patrol Inspection
Sorun Belirtisi
After material or mold change, discoloration and weight fluctuation appear in batches; first article only checks appearance
Neden Analizi
POM is sensitive to heat history and cleanliness; after material change, mass production starts without verifying barrel state changes; weight fluctuation reflects plasticization and check valve status, which appearance cannot reveal
Çözüm
①First article performs three verifications of appearance, weight, and dimension; ②focus patrol inspection on the first few dozen shots after material change; ③include weight data in SPC monitoring; after adjustment, take continuous samples to verify the effect, and resume mass production only after confirming stability
Temel Çıkarım
POM first article verification must include weight; qualified appearance does not mean normal plasticization—data-based patrol inspection prevents batch accidents; after confirming effectiveness, solidify the parameters and practices into the work instruction to prevent recurrence